Milestone Gates
Timeline
Color = derived gate state · hover a tile for its note.marker
Design Freeze — all open decisions closed, schematic finalised
marker
Gerber Release — PCB layout complete, thermal sim done, NTC placed
not started
DVT Gate
marker
First Prototype Bring-up — power-on, PD negotiation, basic output confirmed
marker
DVT Exit — all test cases and VAL scenarios passed
marker
Production Release — design package signed off, ready for manufacture
not started
🏁 Release
MS-001Design Freeze — all open decisions closed, schematic finalised
markerdue 2026-06-24MS-002Gerber Release — PCB layout complete, thermal sim done, NTC placed
markerdue 2026-07-15MS-DVTDVT Gate
not started
1/2 metdue 2026-08-15
met Coverage ≥ 80%
- 16/16 requirements covered (100%)
pending Requirements approved
- REQ-F-07: draft
- REQ-N-01: draft
- REQ-N-03: draft
- REQ-P-03: draft
MS-003First Prototype Bring-up — power-on, PD negotiation, basic output confirmed
markerdue 2026-08-19MS-004DVT Exit — all test cases and VAL scenarios passed
markerdue 2026-09-23MS-005Production Release — design package signed off, ready for manufacture
markerdue 2026-10-14Release / Readiness not started 4/6 met
pending Requirements approved
- REQ-F-07: draft
- REQ-N-01: draft
- REQ-N-03: draft
- REQ-P-03: draft
met Coverage ≥ 100%
- 16/16 requirements covered (100%)
met All test cases pass
- 25/26 passed
- 1 accepted deviation(s): VAL-06
met
No blocking issues open
met
Deviations resolved
pending Interfaces frozen
- INT-PD: not frozen