Milestone Gates

Timeline

Color = derived gate state · hover a tile for its note.
marker
Design Freeze — all open decisions closed, schematic finalised
Jun 24, 2026
marker
Gerber Release — PCB layout complete, thermal sim done, NTC placed
Jul 15, 2026
not started
DVT Gate
Aug 15, 2026· 1/2
marker
First Prototype Bring-up — power-on, PD negotiation, basic output confirmed
Aug 19, 2026
marker
DVT Exit — all test cases and VAL scenarios passed
Sep 23, 2026
marker
Production Release — design package signed off, ready for manufacture
Oct 14, 2026
not started
🏁 Release
· 4/6
MS-001Design Freeze — all open decisions closed, schematic finalised markerdue 2026-06-24
MS-002Gerber Release — PCB layout complete, thermal sim done, NTC placed markerdue 2026-07-15
MS-DVTDVT Gate not started 1/2 metdue 2026-08-15
met Coverage ≥ 80%
  • 16/16 requirements covered (100%)
pending Requirements approved
  • REQ-F-07: draft
  • REQ-N-01: draft
  • REQ-N-03: draft
  • REQ-P-03: draft
MS-003First Prototype Bring-up — power-on, PD negotiation, basic output confirmed markerdue 2026-08-19
MS-004DVT Exit — all test cases and VAL scenarios passed markerdue 2026-09-23
MS-005Production Release — design package signed off, ready for manufacture markerdue 2026-10-14
Release / Readiness not started 4/6 met
pending Requirements approved
  • REQ-F-07: draft
  • REQ-N-01: draft
  • REQ-N-03: draft
  • REQ-P-03: draft
met Coverage ≥ 100%
  • 16/16 requirements covered (100%)
met All test cases pass
  • 25/26 passed
  • 1 accepted deviation(s): VAL-06
met No blocking issues open
met Deviations resolved
pending Interfaces frozen
  • INT-PD: not frozen