Sparrow complete product
ESH10000633 · Rev R1
in_progresselectronics
System-level Sparrow product. Test implementation lives in Maestro TAT package ESH10000633_SparrowUnitTest_v01 (https://github.com/esharpab/testdevelopment-esharp-tat-registry-ESH10000633_SparrowUnitTest_v01).
0%
Coverage
0%
Done
0
Requirements
67
Test Cases
3
Blockers
9
Open Entries
| Relation | Project |
|---|---|
| Depends on | ESH10000534 R4 — Sparrow PoE M.2 module |
| Depends on | ESH10000535 R3 — Sparrow N-Top PCBA |
| Depends on | ESH10000536 R2 — Sparrow Active Load M.2 module |
| Depends on | ESH10000540 R3 — Sparrow Fixture Electronics PCBA |
| Depends on | ESH10000543 R2 — Sparrow Fixture Link PCBA |
| Depends on | ESH10000634 R3 — Sparrow IDC N-Top connector PCBA |
Timeline
Color = derived gate state · hover a tile for its note.marker
Gate 1 — Design Release (all sub-assemblies at Manufacturing in MES; ESH10000634 R3 approved)
marker
Gate 2 — Inventory Procurement (all shortfalls resolved; ESH10000182 build order confirmed)
marker
Gate 3 — Test & Production Infrastructure (ESH10000654 verified; test procedure complete; DUT serials defined)
marker
Gate 4 — First Article (S/N 001 assembled and passed production test)
marker
Gate 5 — Production Run (20 systems assembled + standalone deliverables 10×636, 20×614, 20×637, 20×EPN1000786)
marker
Gate 6 — Delivery (final QC, packaging, delivery documentation complete)
not started
🏁 Release
Status & gates
Chronological — Release is the final gate. Derived & read-only; edit viaplease_milestone_* tools.MS-G1Gate 1 — Design Release (all sub-assemblies at Manufacturing in MES; ESH10000634 R3 approved)
markerdue 2026-05-15MS-G2Gate 2 — Inventory Procurement (all shortfalls resolved; ESH10000182 build order confirmed)
markerdue 2026-06-05MS-G3Gate 3 — Test & Production Infrastructure (ESH10000654 verified; test procedure complete; DUT serials defined)
markerdue 2026-06-05MS-G4Gate 4 — First Article (S/N 001 assembled and passed production test)
markerdue 2026-06-12MS-G5Gate 5 — Production Run (20 systems assembled + standalone deliverables 10×636, 20×614, 20×637, 20×EPN1000786)
markerdue 2026-07-06MS-G6Gate 6 — Delivery (final QC, packaging, delivery documentation complete)
markerdue 2026-07-13Release / Readiness not started 2/6 met
pending Requirements approved
- PWR-26: draft
- PWR-31: draft
- PWR-12: draft
- PWR-13: draft
- PWR-15: draft
- SIG-14: draft
- SIG-04: draft
- SIG-06: draft
- SIG-05: draft
- SIG-07: draft
pending Coverage ≥ 100%
- No requirements in scope
pending All test cases pass
- 25/67 passed
- 42 not yet run
pending No blocking issues open
- E-001: open blocker
- E-004: open blocker
- E-022: open blocker
met
Deviations resolved
met
Interfaces frozen
Test Cases
25 Pass
0 Fail / Deviated
0 N/A
42 Open3 / 67 Maestro impl.
Coverage — 0.0% · Done — 0.0%
| Code | Kind | Title | Severity | Scope | Status | Created |
|---|---|---|---|---|---|---|
E-001 |
notice | G-01: ESH10000182 (Accordion A2 Bare) build order not placed — critical path | blocking | record | open | 2026-05-22 |
E-002 |
notice | G-05: ESH10000637 (PSU Power Cable) procurement — need 40, 0 on hand | warning | record | open | 2026-05-22 |
E-003 |
notice | G-06: EPN1000677 (5-port USB wall charger) — 2 short of 20-unit need | info | record | open | 2026-05-22 |
E-004 |
notice | G-13: ESH10000158 R5 procurement decision DUE 2026-05-27 | blocking | record | open | 2026-05-22 |
E-005 |
notice | ISSUE-001: ESH10000538 M2base loopback — intermittent Sparrow N-Top startup faults | warning | record | open | 2026-05-22 |
E-006 |
notice | 5 user-pin functional groups missing from fixture-electronics-test | warning | record | open | 2026-05-22 |
E-007 |
notice | PT-SIG.04 marginal fail — J6 audio bias-load voltage 0.5% over upper limit | warning | record | open | 2026-05-25 |
E-008 |
notice | ASM-01 | info | record | open | 2026-05-26 |
E-009 |
notice | ASM-02 | info | record | open | 2026-05-26 |
E-010 |
notice | ASM-03 | info | record | open | 2026-05-26 |
E-011 |
notice | Q-AUDIO-001 | info | record | open | 2026-05-26 |
E-012 |
decision | Production test scope: system-level only, not sub-assembly re-test | info | record | closed | 2026-05-26 |
E-013 |
decision | ESH10000539 R1→R2 BOM change disposition | info | record | closed | 2026-05-26 |
E-014 |
decision | Audio test (fe_J6_audio.yaml) limit derivation from full tolerance stack | info | record | closed | 2026-05-26 |
E-015 |
decision | fe_Jx_pwr.yaml limit derivation — 5V_DIV / 12V_DIV / GND from divider tolerance stack | info | record | closed | 2026-05-26 |
E-016 |
decision | fe_J9_pwr.yaml limit derivation — VMON / HOST_V windows from rail spec, ADC chain (ADS7828/AD5593R) and MPIO chain | info | record | closed | 2026-05-26 |
E-017 |
decision | fe_J9_rs485.yaml limit derivation — VMEAS windows from MAX491 V_OD + COM-08 chain accuracy | info | record | closed | 2026-05-26 |
E-018 |
decision | fe_J7_mpio_relay.yaml limit derivation — FE_MPIO loopback + RELAY-fabric (via TA patches) | info | record | closed | 2026-05-26 |
E-019 |
decision | fe_J5_fixed_load.yaml limit derivation — TA pullup + FE GND_SW + 200 K VMEAS-divider loading | info | record | closed | 2026-05-26 |
E-020 |
decision | fe_J5_mpio.yaml limit derivation — AD5592R loopback chain (Sparrow N-Top → FE pass-through → IDC N-Top → TA) | info | record | closed | 2026-05-26 |
E-021 |
decision | fe_J5_pwm.yaml limit derivation — ATMEGA4809 PWM through HiZ MPIO read at 4 V_SET levels | info | record | closed | 2026-05-26 |
E-022 |
notice | System interface freeze pending sub-module sign-off | blocking | action | open | 2026-06-04 |