Sparrow complete product

ESH10000633 · Rev R1

in_progresselectronics

System-level Sparrow product. Test implementation lives in Maestro TAT package ESH10000633_SparrowUnitTest_v01 (https://github.com/esharpab/testdevelopment-esharp-tat-registry-ESH10000633_SparrowUnitTest_v01).

0% Coverage
0% Done
0 Requirements
67 Test Cases
3 Blockers
9 Open Entries

Timeline

Color = derived gate state · hover a tile for its note.
marker
Gate 1 — Design Release (all sub-assemblies at Manufacturing in MES; ESH10000634 R3 approved)
May 15, 2026
marker
Gate 2 — Inventory Procurement (all shortfalls resolved; ESH10000182 build order confirmed)
Jun 5, 2026
marker
Gate 3 — Test & Production Infrastructure (ESH10000654 verified; test procedure complete; DUT serials defined)
Jun 5, 2026
marker
Gate 4 — First Article (S/N 001 assembled and passed production test)
Jun 12, 2026
marker
Gate 5 — Production Run (20 systems assembled + standalone deliverables 10×636, 20×614, 20×637, 20×EPN1000786)
Jul 6, 2026
marker
Gate 6 — Delivery (final QC, packaging, delivery documentation complete)
Jul 13, 2026
not started
🏁 Release
· 2/6

Status & gates

Chronological — Release is the final gate. Derived & read-only; edit via please_milestone_* tools.
MS-G1Gate 1 — Design Release (all sub-assemblies at Manufacturing in MES; ESH10000634 R3 approved) markerdue 2026-05-15
MS-G2Gate 2 — Inventory Procurement (all shortfalls resolved; ESH10000182 build order confirmed) markerdue 2026-06-05
MS-G3Gate 3 — Test & Production Infrastructure (ESH10000654 verified; test procedure complete; DUT serials defined) markerdue 2026-06-05
MS-G4Gate 4 — First Article (S/N 001 assembled and passed production test) markerdue 2026-06-12
MS-G5Gate 5 — Production Run (20 systems assembled + standalone deliverables 10×636, 20×614, 20×637, 20×EPN1000786) markerdue 2026-07-06
MS-G6Gate 6 — Delivery (final QC, packaging, delivery documentation complete) markerdue 2026-07-13
Release / Readiness not started 2/6 met
pending Requirements approved
  • PWR-26: draft
  • PWR-31: draft
  • PWR-12: draft
  • PWR-13: draft
  • PWR-15: draft
  • SIG-14: draft
  • SIG-04: draft
  • SIG-06: draft
  • SIG-05: draft
  • SIG-07: draft
pending Coverage ≥ 100%
  • No requirements in scope
pending All test cases pass
  • 25/67 passed
  • 42 not yet run
pending No blocking issues open
  • E-001: open blocker
  • E-004: open blocker
  • E-022: open blocker
met Deviations resolved
met Interfaces frozen
Blocked 3 blocking entries
🔗 Composition 6 dependencies need attention: ESH10000534 R4 (amber), ESH10000535 R3 (amber), ESH10000536 R2 (amber), ESH10000540 R3 (amber), ESH10000543 R2 (amber), ESH10000634 R3 (amber)

Test Cases

25 Pass 0 Fail / Deviated 0 N/A 42 Open3 / 67 Maestro impl.

Coverage — 0.0% · Done — 0.0%

22 of 22
CodeKindTitleSeverityScopeStatusCreated
E-001 notice G-01: ESH10000182 (Accordion A2 Bare) build order not placed — critical path blocking record open 2026-05-22
E-002 notice G-05: ESH10000637 (PSU Power Cable) procurement — need 40, 0 on hand warning record open 2026-05-22
E-003 notice G-06: EPN1000677 (5-port USB wall charger) — 2 short of 20-unit need info record open 2026-05-22
E-004 notice G-13: ESH10000158 R5 procurement decision DUE 2026-05-27 blocking record open 2026-05-22
E-005 notice ISSUE-001: ESH10000538 M2base loopback — intermittent Sparrow N-Top startup faults warning record open 2026-05-22
E-006 notice 5 user-pin functional groups missing from fixture-electronics-test warning record open 2026-05-22
E-007 notice PT-SIG.04 marginal fail — J6 audio bias-load voltage 0.5% over upper limit warning record open 2026-05-25
E-008 notice ASM-01 info record open 2026-05-26
E-009 notice ASM-02 info record open 2026-05-26
E-010 notice ASM-03 info record open 2026-05-26
E-011 notice Q-AUDIO-001 info record open 2026-05-26
E-012 decision Production test scope: system-level only, not sub-assembly re-test info record closed 2026-05-26
E-013 decision ESH10000539 R1→R2 BOM change disposition info record closed 2026-05-26
E-014 decision Audio test (fe_J6_audio.yaml) limit derivation from full tolerance stack info record closed 2026-05-26
E-015 decision fe_Jx_pwr.yaml limit derivation — 5V_DIV / 12V_DIV / GND from divider tolerance stack info record closed 2026-05-26
E-016 decision fe_J9_pwr.yaml limit derivation — VMON / HOST_V windows from rail spec, ADC chain (ADS7828/AD5593R) and MPIO chain info record closed 2026-05-26
E-017 decision fe_J9_rs485.yaml limit derivation — VMEAS windows from MAX491 V_OD + COM-08 chain accuracy info record closed 2026-05-26
E-018 decision fe_J7_mpio_relay.yaml limit derivation — FE_MPIO loopback + RELAY-fabric (via TA patches) info record closed 2026-05-26
E-019 decision fe_J5_fixed_load.yaml limit derivation — TA pullup + FE GND_SW + 200 K VMEAS-divider loading info record closed 2026-05-26
E-020 decision fe_J5_mpio.yaml limit derivation — AD5592R loopback chain (Sparrow N-Top → FE pass-through → IDC N-Top → TA) info record closed 2026-05-26
E-021 decision fe_J5_pwm.yaml limit derivation — ATMEGA4809 PWM through HiZ MPIO read at 4 V_SET levels info record closed 2026-05-26
E-022 notice System interface freeze pending sub-module sign-off blocking action open 2026-06-04